|
CAPITAL PROJECTS
PROGRESS – 16th May 2008
Well we finally reached the top of La Vallee with the new sewer pipe,
fought our way through the ground water, found a way round the unexpected
well in the middle of the road, and installed the new electric cables which
will eventually form part of the electricity distribution network for the Island. The damaged manhole was repaired and the pipe
connection remade. The trench in La Vallee is now being backfilled for the
last time and Ronez are about to apply the tarmac, so at last the roads will
soon be opened again and the disruption and disturbance will largely cease.
Now the work enters the Vallee
Gardens in a big way,
and hopefully no more big problems will be encountered and the work should
race through to the Island Hall. Am I tempting fate?

The sewers from Stoney
Lane and Church Street are now permanently
connected into the new manhole. The old sewer which runs from the Island Hall
through the Vallee
Gardens has also now
been temporarily connected into the new one at the top of La Vallee, so that
all the foul water from town now passes through the new sewer pipes. The
installation of the remaining part of the new sewer through the Vallee Gardens to the Island Hall can now be
achieved without disturbing the normal sewage flow. Once the new sewer is
complete and connected to the existing sewer at the back of the Island Hall
this temporary connection will be broken and the old sewer sealed off.
We are entering the last stages of the work now, and can see the light
at the end of the tunnel. If all goes well we can expect to say “The End” by
the end of June. There have been plenty of problems on the way, and there is
always the possibility of more arising before we have finished, but as
someone said, there is no such thing as problems, only solutions, and of
course the solutions have been found by the very competent contractor.
At the Courthouse the work of renovating the Court building itself is
rapidly reaching a conclusion. The additional electrical work for the new
audio and recording systems is complete and the specialist equipment supplier
is due here by the time this article appears. Scaffolding removal is at last
proceeding and the improved face of the building will soon now be seen, to
add to the very high quality appearance of all the properties in QEII Street. The
Courtroom itself is now looking quite magnificent and a credit to the
contractor. The painting and decorating is rapidly approaching completion and
then the carpeting will add the final touches. It maybe a trifle optimistic
but it is hoped to allow the first
Court session of June to take place in the newly
refurbished Courtroom.

|
|
CAPITAL PROJECTS
PROGRESS – 7th May 2008
Isn’t it always the way? You
think you are past all your big problems and are on a nice straight easy run
for a while and WHAM, you run into another big one!
Having reached the top of La
Vallee we were all looking forward to getting out of the road and to a nice
easy run through the grounds of the school and the Vallee Gardens,
when a rather strange and unknown Victorian brick culvert made its
appearance, leaking like a sieve and pouring clean water into the trench. No
one seemed to know where it was coming from or going to, except that the
water appeared to end up in the little stream running in front of the houses.
It had to go, as it was directly in the way of the new sewer, and when it was
broken and the water was being pumped away the little stream stopped – which
rather upset one or two residents. Further excavation revealed that there
were apparently TWO culverts, one of which is dry, and then, of all things, a
well was discovered, which had been covered over by the road and which
apparently was once the source of supply to the nearby cattle trough. The
good news was that when the trench was backfilled with a layer of stone the
water found its way back into the stream again. The bad news was that the ground
was so poor that the trench collapsed and caused severe damage to the newly
installed manhole.
However, as someone said,
there is no such thing as problems, only solutions, and of course a solution
was found by the very competent contractor and the work of laying the sewer
pipes is continuing into the school grounds and on into the Gardens. The
damaged manhole will be repaired in situ in a week or so.
The cobbled road to Platte
Saline has been re-cobbled and looks very smart, and we are getting near the
end of the disruptive part of the job now, though it is not quite clear yet.
Over the next three or four weeks the trench in Vallee will be partially
reopened, the electric cable will be laid, the trench backfilled again, and
then probably starting on 19 May Ronez will come along with tarmac – and that
should see the roads back to normal. There will still be some heavy traffic
moving about so caution is still required.

Dare it be said? With
hopefully no more unforeseen obstructions, it is anticipated that the project
will be completed in early June.
At the Courthouse the work
of renovating the Court building itself is going well. The additional
electrical work is largely complete and the specialist equipment supplier is
expected shortly to install and commission the equipment. Scaffolding removal
still seems to be a bit of a problem but hopefully by the time this appears
it will be done. There is still quite a lot of painting to complete – it is a
pretty big building – but it is “getting there”, and then there is the
carpeting. When finished, which should not now be too long, it will be a
smart looking building, inside and out.

|
|
Notice of Road
Closures – Vallee Sewer.
The
work of renewing the main sewer is now advancing onto the public highways
which will involve closure of roads to ensure safety during the construction
works.
Commencing
from Tuesday 8th January 2008 Crabby Road will be closed to
through traffic until approximately the end of February. Initially the road
will be closed at a point just above the hospital entrance (at the top of the
cobbled road leading to Fort Doyle), and the point of closure will be moved
towards La Vallee junction as the work progresses.
Access
will only be allowed to properties along Crabby Road itself, and then this
will be limited to pedestrian access whilst the work is underway adjacent to
that property.
Further
closures will be necessary at a future date. Advance notice will be given as
soon as practical.
Please
also note that the dirt road along Platte Saline in front of the houses is a
private road and this is not an alternative route.
Thank
you for your co-operation in this matter.
Julie Turner
States Engineer
|